Construction activities have been suspended for the winter and will resume in the spring as weather conditions permit. A construction update will be provided 2 weeks before construction is expected to resume.
Click the button below to get answers to the most commonly asked questions. Complete the adjacent form to sign up to receive email notifications when the schedule or other important information is updated on this page.
Overall Project Schedule This schedule represents the most up-to-date information received by the Contractor. The construction schedule can and will change for various reasons. Changes to the construction schedule will be updated here as soon as practical.
2024 Improvements
Work on Main Street, 6th Avenue, and 2nd Street was not completed in 2023.
Maple Drive sanitary sewer, water, and streets.
Concrete paving in the alley west of 5th Avenue.
Replacement of the flood control storm sewer lift station on the west side of County Road 11 at the intersection of 2nd Street.
Project Purpose The project's purpose is to replace aging streets and utility infrastructure within the Original Townsite and Maplewood neighborhoods. The underground utility infrastructure in the Original Townsite and Maplewood neighborhoods was installed in the early 1960s and early 1970s, respectively. Today, the streets and underground utilities are at or nearing their useful life. The project will also replace the undersized flood protection lift station at 2nd Street and County Road 11. Additional upgrades will include parking improvements in front of City Hall and concrete paving of the alley between 5th Avenue and 6th Avenue.
Project Overview
The map to the left shows the general areas impacted by the project. Click the button below to see a detailed map showing specific improvements to be completed by the project.